What is the Party Wall etc. Act 1996?
The Party Wall etc. Act 1996 is legislation in England and Wales that governs building work affecting shared or neighbouring structures. Its purpose is to let development proceed while protecting adjoining properties and their occupiers
The Act covers three main types of work:
- Alterations to shared structures, such as party walls (i.e. the wall between you and the neighbour) or the floors between flats.
- Excavations within 3 metres and to a depth greater than the foundations of your neighbour’s house or wall.
- New walls built on, or up to, a boundary line between two properties.
If your project falls under the Act, you must serve notice on your neighbour. If they don’t consent, both parties appoint surveyors, who agree a legally binding Party Wall Award that sets out how work can proceed for both parties
The Act and the awards will set out the following :
- Neighbours shouldn’t experience unnecessary inconvenience from the works.
- Any damage caused must be repaired or compensated.
- The homeowner carrying out the work has rights too, such as being allowed access to a neighbour’s land if it’s needed to complete the works.
For Building OwnersThose Doing the Work
- You must serve formal Party Wall Notice(s) before starting relevant notifiable works.
- The act gives you certain rights, such as access to a neighbour’s land if needed.
- Can proceed with work once consent or a Party Wall Award is in place.
- Must avoid causing unnecessary inconvenience to your neighbours..
- Responsible for repairing or compensating for any damage caused by your works cause to your neighbour.
For Adjoining OwnersThe Neighbours
- You should receive formal notice of proposed works by your neighbours
- You can give consent, or dissent and trigger the dispute resolution process.
- Entitled to appoint their own surveyor (at the building owner’s cost).
- Protected from damage and disruption and the Act provide a clear route ot resolve issues of damage.
- Benefit from a clear legal process if they disagree with the notifiable works and how your interests can be represented under the act..
THE PARTY WALL PROCESS
1. Serving Notice
The building owner must formally notify neighbours of any proposed works covered by the Act. Notices usually give 1–2 months’ lead time, depending on the type of work.
2. Neighbour’s Response
The adjoining owner has 14 days to reply. They can:
- Consent-to the works.
- Dissent-and agree to use a single surveyor.
- Dissent-and appoint their own surveyor. If no reply is given, it is treated as dissent.
3. Schedule of Condition
A surveyor records the neighbour’s property condition (photos and notes) before works start. This protects both sides if damage is later claimed.
4. Party Wall Award
Surveyors agree to a legally binding document that sets out how and when the works must be carried out. It may include specific methods or safeguards to protect the adjoining property.
5. Service of the Award
The final Award is served on both owners. Once notice periods have expired, the building owner can legally begin the works.
6. Post-Works Inspection
For higher-risk projects, the surveyor may revisit once the works are complete to check for damage. If damage is found, it must either be repaired by the building owner’s contractor or compensated.


Why Choose Toynbee Associates for Party Wall Matters?
- Specialist Expertise We focus on Party Wall work day in, day out, so you’ll get advice that’s accurate, practical, and legally sound.
- Trusted Guidance From serving notices to agreeing the Awards, we handle the whole process and explain every step in plain English.
- Impartial & Professional Whether acting for building owners or neighbours, we make sure the Act is applied fairly and disputes are resolved quickly.
- Protecting Your Interests We prepare thorough Schedules of Condition and ensure any risks are minimised before work begins.
- Experience That Counts Having managed hundreds of Party Wall cases across London and the Home Counties, we know how to prevent problems before they arise.
- Peace of Mind With Toynbee Associates, you can move your project forward confidently, knowing your legal obligations are met and your neighbour’s rights are respected.
What We Deliver
How We Accomplish It
We move your project forward confidently and without legal risks.
Our combined experience and multidisciplinary team will ensure all your legal obligations under the Act are met and your neighbour’s rights are respected, providing you with total peace of mind.
You feel fully informed and up to date as the process progresses, whichever side of the wall you are.
We provide trusted guidance by handling the entire Party Wall process from serving notices to agreeing the Award and explaining every step in clear, plain English.
We avoid costly complications and potential project delays.
We get the party wall awards in place quickly. Our Specialist surveyors, engineers and architects focus solely on Party Wall work. We apply these skills, along with our own in-house software to keep the process moving forward.
Maintain positive neighbourly relationships and achieve a quick resolution.
We understand how people feel about this and ensure awards are resolved quickly and professionally for both building owners and adjoining owners. Our experience ensures that we apply the Act fairly and impartially, and we deal with this on a daily basis.
We protect your investment and minimise property risk from the outset.
This ensures any issues of damage can be properly identified later on. We prepare thorough Schedules of Condition to record the condition of affected properties prior to works starting.
We rely on deep experience for a seamless and problem-free process.
We apply the knowledge from hundreds of Party Wall cases across London and with over 75 years of combined experience in Party Wall matters, to deliver advice that is accurate, practical and applicable to your project.
Speak to the team same day and get a FREE quote within 24 hours.
Submit your enquiry and our skilled and accredited team will get in touch shortly and we guarantee your Party Wall quote within 24 hours of initial contact.
Talk to Accredited Party Wall Surveyors today
FAQs: Party Wall Process
Yes, if your planned work affects a shared wall, boundary or structure, the Party Wall etc. Act 1996 requires that you serve notice to all affected neighbours. Common examples include extensions, loft conversions, basement digs or any excavation close to another property. We can quickly confirm whether your work qualifies and, if so, prepare and serve the correct notices on your behalf.
They can dissent to the notice, but that does not mean they can block your project. It simply means they want a surveyor to act on their behalf to review the plans and make sure their property is protected. This triggers the Party Wall Award process, which is designed to resolve matters fairly and allow work to proceed while managing risk.
Fees vary depending on the type of work, the number of surveyors involved and how complex the project is. Typically, if you are the Building Owner carrying out the works, you will be responsible for reasonable surveyor fees on both sides. We offer fixed-fee quotes where possible and will always explain costs before you commit.
You can serve your own Party Wall Notice, but if it’s done incorrectly, it may be invalid. This could delay your project or open you up to disputes later. Notices must follow a strict format and be served properly. It’s usually best to have a professional surveyor handle the process, especially if you’re dealing with tight timelines or sensitive neighbours.
Notices must be served at least one or two months before work starts, depending on the type. We recommend planning ahead and serving notices as early as possible. This gives everyone time to review the proposal and avoids holding up your construction schedule.
If the Adjoining Owner does not reply within 14 days, they are considered to have “dissented.” You are then required to appoint a Party Wall Surveyor for them. This ensures the process moves forward fairly. It is one of the reasons why having a surveyor manage the timeline is useful — we keep things on track.
This depends on how complex the project is and how responsive everyone is. If notices are consented to quickly, things can move in a matter of weeks. If surveyors are appointed and a Party Wall Award is needed, it typically takes around 4 to 8 weeks from start to finish. We’ll give you realistic timeframes based on your specific project.
If you’re the Adjoining Owner and damage occurs, the Schedule of Condition prepared before the works began will serve as a clear record. The Party Wall Award sets out how damage should be dealt with, including options for repair or compensation. We will reinspect the property after the works and help ensure any issues are resolved properly and fairly.