Challenges We Faced

We worked on a ground-floor flat in Fulham that had five sets of adjoining owners.

The Solutions Developed

We provided guidance and advice to the building owner on what was required to complete and agree the awards. We also negotiated access and methods for rights of access over the adjoining owners’ land. Furthermore, we reviewed the engineer’s details and temporary works details, and provided feedback on architectural details (where the client had not retained their architect), all to speed up the process.

The Results Achieved

Our proactive approach, including reviewing and advising on submissions to adjoining owners’ surveyors, helps to speed up the process. We use internal software to ensure our team is aware of all award stages and can keep the process moving, and to provide regular client updates.

It took us 7 weeks and 5 days to get the awards served and in place from the service of notices to the signed awards on all five owners. This was quicker than our stated minimum period of 8-12 weeks.

Location

Fulham, London

Developer

Private Homeowner

Privacy Preference Center